You can translate the question and the replies:

How do I change the order of load processes in the Denodo 8 scheduler web interface?

I have 9 views in my jobb and managed and need to change the order of them because one needs to be run before another. The interface only allows med to add new load processes and not change the order of them. Please advice how I can do this /Peter
user
14-09-2023 04:14:11 -0400
code

1 Answer

Hi, In the "Extraction Section" within the "Load Processes" window, you have the option to select and drag to rearrange the execution order of the views as needed. Hope this helps!