how to get the prior job execution status in scheduler.

I have 5-6 jobs which has dependency on each other. I want to run the job even though it's dependant job fails. can i refer to prior job status in dependant job so i can conditionally execute it. e.g. if prior job execute_status = 'success' then JOB1 else JOB2.
user
01-11-2016 15:45:09 -0400
code

1 Answer

Hi, There is no built in way to conditionally execute jobs. You can try writing a script to trigger a conditional dependency. You can, however, set jobs to execute even if the ones it is dependent on have failed. Do this by checking the “Execute this job even though any of its dependencies finish with error” box in the trigger section of a job. Hope this helps!
Denodo Team
02-11-2016 17:40:19 -0400